Answer: Two days Explanation: There are several factors that would alter this. |
Jack of trades services |
Answer: Three days Explanation: If the driveway has already been prepared. Meaning that the surface is flat, required membranes have been applied and all other best practices are already met this is a reasonable timeline with 2 installers. The tile can be installed in two days and the final day is to add the grout and required sealants. |
Rafael Tile Works |
Answer: Four days Explanation: While it's possible for one person to complete the installation within three to four days, it's key to consider the complexity of the project, the skill level of the installer, and any various factors that could impact the timeline. Consulting with a professional contractor can provide a more accurate estimate based on your specific project requirements. |
Construction Services & Repairs |
|
ProMatcher |
Answer: Not sure Explanation: I work almost inside Job and Bigger Pieces |
AMG Flooring & Paint, Inc. |
Answer: Three days Explanation: (26% of 83 votes): three days |
Chos cortez construcción LLC |
Answer: Two days Explanation: One day preparing, Excavating, leveling
the second day laying pavers |
New Exteriors LLC |
|
ProMatcher |
Answer: Four days Explanation: Ussually its more than one person.but it would take 3 to 4 days for one person to install this square footage |
Concrete Designs |
Answer: Seven days Explanation: Of course it depends on equipment available and existing driveway proper excavation of materials. Adequate base added and compacted in layers as well as hauling away excess material
It can take a couple of wwwks or as little as 3 or 4 days with experience and equipment |
Mr Falls Tree Experts |
Answer: One day Explanation: Really nothing to it as long as he's moving along and not take as many cigarette breaks as normal lol. Shouldn't take more then a day or else your in the wrong industry. |
SouthPac Construction |
|
ProMatcher |
Answer: Six days Explanation: to do it this job from demodition grade put base and sand and layout brick sealing with polysand pass the compact plate wash and sealing |
alvaradomasonry |
Answer: Not sure Explanation: It would depend on site conditions as well as the individual. It could take a few days or longer. If conditions are good this type of job could take approx. 2 days. |
Design4 |
Answer: Not sure Explanation: This question is to vague to answer correctly. There is no indication what the sub surface is. Does excavation need to be done? What is the level of compaction? How close is the job site to where the pavers are stored. But to provide an answer 800 square feet of pavers could be installed in a 1-2 days. |
A New Design Landscape & Stone, Inc. |
|
ProMatcher |
Answer: Three days Explanation: The amount of time, can vary depending on the particular paver being used. |
Land Tech Landscapes |
Answer: Three days Explanation: Safe to say three days! One day is prep and two for install |
DIRTCO CONSTRUCTION |
Answer: One day Explanation: I have did it in 1day |
HAMMER & SONS CONSTRUCTION |
|
ProMatcher |
Answer: Three days Explanation: ground preparation along with installation of pavers can take hours for a few square feet. |
Concrete & Beauty Design |
Answer: Not sure Explanation: We don't do brick driveways. We do only stone installations |
1964 |
Answer: Four days Explanation: An experienced installer installing proper base and a basic paver pattern should be able to install 800 square feet in 4 days. |
Cornerstone Land Management |
|
ProMatcher |
Answer: Not sure Explanation: This anser has too many variables to give an answer without seeing the project first. |
Axiom Construction |
Answer: One day Explanation: Experience is the key! |
Sod Sales Direct |
Answer: Two days Explanation: First day need to dig 8 to 9 inches deep just because it's a driveway. Then need to install 8 inches of compacted abc stone, need to compact with a ply tamp.second day, need to install 2 inches of sand and start installing your pavers and to make sure they are level. |
Garcias Concrete Service LLC, |
|
ProMatcher |
Answer: Four days Explanation: 800 sq feet of pavers should be able to be cut out, gravel installed, labor and cut in within a four day period. |
Evans Landscapes &Design Inc. |
Answer: One day Explanation: With 3 employees. |
Morales Project Corp. |
Answer: Four days Explanation: These are time consuming |
S7 CONCRETE |
|
ProMatcher |
Answer: Two days Explanation: Prep work |
dlb construction |
Answer: Seven days Explanation: The installation of pavers or bricks is the fasted part of the project. Proper preparation takes the most time. For one man or woman to install an 800 sq ft patio, I would allow at least 7 days. |
Lanese Landscaping |
Answer: Five days Explanation: You will need to order 20 yard dumpster 1/2 day, 2 general laborer's 2 days prep work and clean-up. @ day laborer's to lay brick pavers 1 day and 1/2, 1 day to finish sand and concrete mix topping and clean up. |
JE Restoration, LLC |
|
ProMatcher |
Answer: Three days Explanation: It could take 2 -7 days depending on their level of expertise. We are ICPI Certified Paver Installer and could have a job like this done in 1-2 days. Depending on the site conditions. |
Quality Contractors |
Answer: Not sure Explanation: A professional company would not send just a single person out for a project of this kind. |
Lonestar Patio Covers |
Answer: Two days Explanation: This is a two day job for 1 person |
Carvalho Pavers |
|
ProMatcher |
Answer: Four days Explanation: Always allow an extra day for clean up, about four days should do it. |
Robbie Lee Construction |
Answer: Three days Explanation: depending on the expertise, but for one person is hard to go faster |
Carpentry Solutions |
Answer: Three days Explanation: It really depends on the design,edge,grade,etc. Typically a straight drive with a basic patern on level ground should be a three day job. |
Unique visions landscape design |
|
ProMatcher |
Answer: Five days Explanation: I would never expect one person to handle the project, the prep work, the overall work load should be performed with proper compacting equipment, leveling equipment etc... I Would not bid the work out for a one man crew so I would say have fun for a week or so... |
Nu-Face of PA |