Brick Driveway Installation  Promote Your Business
Brick Driveway Installation
ProMatch
Directory
Cost Report
 

How long does it take one person to install a 40' x 20' brick driveway using 12"x 10" pavers?

One day
8%
Two days
20%
Three days
27%
Four days
12%
Five days
6%
Six days
3%
Seven days
8%
Not sure
12%
Get Free Quotes Today!
Question: How long does it take one person to install a 40' x 20' brick driveway using 12"x 10" pavers?
Top Answer (27% of 91 votes): Three days.

Answer: Two days
Explanation: There are several factors that would alter this.
Jack of trades services
Answer: Three days
Explanation: If the driveway has already been prepared. Meaning that the surface is flat, required membranes have been applied and all other best practices are already met this is a reasonable timeline with 2 installers. The tile can be installed in two days and the final day is to add the grout and required sealants.
Rafael Tile Works
Answer: Four days
Explanation: While it's possible for one person to complete the installation within three to four days, it's key to consider the complexity of the project, the skill level of the installer, and any various factors that could impact the timeline. Consulting with a professional contractor can provide a more accurate estimate based on your specific project requirements.
Construction Services & Repairs
ProMatcher
Answer: Not sure
Explanation: I work almost inside Job and Bigger Pieces
AMG Flooring & Paint, Inc.
Answer: Three days
Explanation: (26% of 83 votes): three days
Chos cortez construcción LLC
Answer: Two days
Explanation: One day preparing, Excavating, leveling the second day laying pavers
New Exteriors LLC
ProMatcher
Answer: Four days
Explanation: Ussually its more than one person.but it would take 3 to 4 days for one person to install this square footage
Concrete Designs
Answer: Seven days
Explanation: Of course it depends on equipment available and existing driveway proper excavation of materials. Adequate base added and compacted in layers as well as hauling away excess material It can take a couple of wwwks or as little as 3 or 4 days with experience and equipment
Mr Falls Tree Experts
Answer: One day
Explanation: Really nothing to it as long as he's moving along and not take as many cigarette breaks as normal lol. Shouldn't take more then a day or else your in the wrong industry.
SouthPac Construction
ProMatcher
Answer: Six days
Explanation: to do it this job from demodition grade put base and sand and layout brick sealing with polysand pass the compact plate wash and sealing
alvaradomasonry
Answer: Not sure
Explanation: It would depend on site conditions as well as the individual. It could take a few days or longer. If conditions are good this type of job could take approx. 2 days.
Design4
Answer: Not sure
Explanation: This question is to vague to answer correctly. There is no indication what the sub surface is. Does excavation need to be done? What is the level of compaction? How close is the job site to where the pavers are stored. But to provide an answer 800 square feet of pavers could be installed in a 1-2 days.
A New Design Landscape & Stone, Inc.
ProMatcher
Answer: Three days
Explanation: The amount of time, can vary depending on the particular paver being used.
Land Tech Landscapes
Answer: Three days
Explanation: Safe to say three days! One day is prep and two for install
DIRTCO CONSTRUCTION
Answer: One day
Explanation: I have did it in 1day
HAMMER & SONS CONSTRUCTION
ProMatcher
Answer: Three days
Explanation: ground preparation along with installation of pavers can take hours for a few square feet.
Concrete & Beauty Design
Answer: Not sure
Explanation: We don't do brick driveways. We do only stone installations
1964
Answer: Four days
Explanation: An experienced installer installing proper base and a basic paver pattern should be able to install 800 square feet in 4 days.
Cornerstone Land Management
ProMatcher
Answer: Not sure
Explanation: This anser has too many variables to give an answer without seeing the project first.
Axiom Construction
Answer: One day
Explanation: Experience is the key!
Sod Sales Direct
Answer: Two days
Explanation: First day need to dig 8 to 9 inches deep just because it's a driveway. Then need to install 8 inches of compacted abc stone, need to compact with a ply tamp.second day, need to install 2 inches of sand and start installing your pavers and to make sure they are level.
Garcias Concrete Service LLC,
ProMatcher
Answer: Four days
Explanation: 800 sq feet of pavers should be able to be cut out, gravel installed, labor and cut in within a four day period.
Evans Landscapes &Design Inc.
Answer: One day
Explanation: With 3 employees.
Morales Project Corp.
Answer: Four days
Explanation: These are time consuming
S7 CONCRETE
ProMatcher
Answer: Two days
Explanation: Prep work
dlb construction
Answer: Seven days
Explanation: The installation of pavers or bricks is the fasted part of the project. Proper preparation takes the most time. For one man or woman to install an 800 sq ft patio, I would allow at least 7 days.
Lanese Landscaping
Answer: Five days
Explanation: You will need to order 20 yard dumpster 1/2 day, 2 general laborer's 2 days prep work and clean-up. @ day laborer's to lay brick pavers 1 day and 1/2, 1 day to finish sand and concrete mix topping and clean up.
JE Restoration, LLC
ProMatcher
Answer: Three days
Explanation: It could take 2 -7 days depending on their level of expertise. We are ICPI Certified Paver Installer and could have a job like this done in 1-2 days. Depending on the site conditions.
Quality Contractors
Answer: Not sure
Explanation: A professional company would not send just a single person out for a project of this kind.
Lonestar Patio Covers
Answer: Two days
Explanation: This is a two day job for 1 person
Carvalho Pavers
ProMatcher
Answer: Four days
Explanation: Always allow an extra day for clean up, about four days should do it.
Robbie Lee Construction
Answer: Three days
Explanation: depending on the expertise, but for one person is hard to go faster
Carpentry Solutions
Answer: Three days
Explanation: It really depends on the design,edge,grade,etc. Typically a straight drive with a basic patern on level ground should be a three day job.
Unique visions landscape design
ProMatcher
Answer: Five days
Explanation: I would never expect one person to handle the project, the prep work, the overall work load should be performed with proper compacting equipment, leveling equipment etc... I Would not bid the work out for a one man crew so I would say have fun for a week or so...
Nu-Face of PA
Get Free Quotes Today!
Find Local Pros
Free Brick or Concrete Paver Installation Cost Estimates

Related Questions

Should a Brick Driveway Be Sealed?Top answer: In some cases

How Long Should I Wait Before Parking on New Brick Driveway?Top answer: 1 day

Can you paint a brick driveway?Top answer: Yes

How Much Does Brick Driveway Installation Cost?



Free Cost Estimates   |   Brick Driveway Companies Directory   |   Brick Driveway Installation Cost Report   |   Free Business Listing



All users of ProMatcher.com are subject to our terms of use.

Home   |   Articles & Videos   |   Affiliates   |   Networking Groups   |   Search by Category

Terms of Use   |   Privacy   |   Partner Network   |   Your Privacy Choices   |   About Us   |   Contact Us   |   Member Login

©2003-2024 - VentureStreet, LLC

Join Our Business Network