Answer: Five days Explanation: Installing a 40' x 20' brick driveway (800 sq. ft.) using 12"x10" pavers is a labor-intensive process for one person. The job involves site preparation, excavation, base installation, laying pavers, cutting edges, and sealing.
Day 1: Excavation and site preparation (removing old materials, grading, and compacting).
Day 2: Installing the base layer (gravel, sand, and compacting).
Day 3-4: Laying pavers and cutting edges for a proper fit.
Day 5: Sanding joints, compacting pavers, and sealing.
With no delays or complications, a single skilled worker can complete the project in approximately five days, but additional time may be needed for intricate patterns or weather-related delays. |
Pro Services |
Answer: Two days Explanation: There are several factors that would alter this. |
Jack of trades services |
Answer: Three days Explanation: If the driveway has already been prepared. Meaning that the surface is flat, required membranes have been applied and all other best practices are already met this is a reasonable timeline with 2 installers. The tile can be installed in two days and the final day is to add the grout and required sealants. |
Rafael Tile Works |
|
ProMatcher |
Answer: Four days Explanation: Several days to lay the base, 2 to lay pavers and cut edges. |
TJB-INC Landscape & Drainage Contractor |
Answer: Not sure Explanation: I work almost inside Job and Bigger Pieces |
AMG Flooring & Paint, Inc. |
Answer: Three days Explanation: (26% of 83 votes): three days |
Chos cortez construcción LLC |
|
ProMatcher |
Answer: Six days Explanation: Nearly 800 pavers. That's alot before dinner time |
Kon-Krete Specialist |
Answer: Four days Explanation: Ussually its more than one person.but it would take 3 to 4 days for one person to install this square footage |
Concrete Designs |
Answer: Seven days Explanation: Of course it depends on equipment available and existing driveway proper excavation of materials. Adequate base added and compacted in layers as well as hauling away excess material
It can take a couple of wwwks or as little as 3 or 4 days with experience and equipment |
Mr Falls Tree Experts |
|
ProMatcher |
Answer: Three days Explanation: At a rate of 400 per day, plus some form work and so forth, three days should be ample.
This could be a trick question though. It doesn't specify the hours worked in a day, so let's say the brick layer works a full 24 hours. This should be ample time to lay the driveway; Just keep the coffee coming. |
Dolphin Pools |
Answer: Six days Explanation: to do it this job from demodition grade put base and sand and layout brick sealing with polysand pass the compact plate wash and sealing |
alvaradomasonry |
Answer: Not sure Explanation: It would depend on site conditions as well as the individual. It could take a few days or longer. If conditions are good this type of job could take approx. 2 days. |
Design4 |
|
ProMatcher |
Answer: Seven days Explanation: You have to prep for the blocks that's one maybe two days and then figure 200 square feet a day there you go six seven days |
Foster Construction |
Answer: Three days Explanation: The amount of time, can vary depending on the particular paver being used. |
Land Tech Landscapes |
Answer: Three days Explanation: Safe to say three days! One day is prep and two for install |
DIRTCO CONSTRUCTION |
|
ProMatcher |
Answer: Not sure Explanation: Its all about the accessibility of the materials and if there is any slopes or drain that must be worked |
h and h company |
Answer: Three days Explanation: ground preparation along with installation of pavers can take hours for a few square feet. |
Concrete & Beauty Design |
Answer: Not sure Explanation: We don't do brick driveways. We do only stone installations |
1964 |
|
ProMatcher |
Answer: Three days Explanation: if were all ready prepped it could be done in 2 days |
Rock Star Masonry |
Answer: Not sure Explanation: This anser has too many variables to give an answer without seeing the project first. |
Axiom Construction |
Answer: One day Explanation: Experience is the key! |
Sod Sales Direct |
|
ProMatcher |
Answer: Seven days Explanation: A driveway install can have many variables which can dictate a drastic difference in time. Expect 1-2 days for excavation, 1-2 days for the base installation, 2-3 days for pattern layout, and 1-3 days for cuts, final adjustments, and site cleanup. |
Blue Lotus Landscaping |
Answer: Four days Explanation: 800 sq feet of pavers should be able to be cut out, gravel installed, labor and cut in within a four day period. |
Evans Landscapes &Design Inc. |
Answer: One day Explanation: With 3 employees. |
Morales Project Corp. |
|
ProMatcher |
Answer: Three days Explanation: The size of the paver would allow completion of this task in about 4 days. However there are circumstances that would require a longer install |
Salinas Lawn Services |
Answer: Two days Explanation: Prep work |
dlb construction |
Answer: Seven days Explanation: The installation of pavers or bricks is the fasted part of the project. Proper preparation takes the most time. For one man or woman to install an 800 sq ft patio, I would allow at least 7 days. |
Lanese Landscaping |
|
ProMatcher |
Answer: Three days Explanation: www.facebook.com/eliteconst |
Elite Construction |
Answer: Three days Explanation: It could take 2 -7 days depending on their level of expertise. We are ICPI Certified Paver Installer and could have a job like this done in 1-2 days. Depending on the site conditions. |
Quality Contractors |
Answer: Not sure Explanation: A professional company would not send just a single person out for a project of this kind. |
Lonestar Patio Covers |
|
ProMatcher |
Answer: Four days Explanation: depends on weather and such. |
Major League Construction |
Answer: Four days Explanation: Always allow an extra day for clean up, about four days should do it. |
Robbie Lee Construction |
Answer: Three days Explanation: depending on the expertise, but for one person is hard to go faster |
Carpentry Solutions |
|
ProMatcher |
Answer: Two days Explanation: One day to prep area and a second to install |
Greener Touch Landscaping llc |
Answer: Five days Explanation: I would never expect one person to handle the project, the prep work, the overall work load should be performed with proper compacting equipment, leveling equipment etc... I Would not bid the work out for a one man crew so I would say have fun for a week or so... |
Nu-Face of PA |