Answer: Five days Explanation: Depending |
GL LANDSCAPE SERVICE LLC |
Answer: Five days Explanation: Installing a 40' x 20' brick driveway (800 sq. ft.) using 12"x10" pavers is a labor-intensive process for one person. The job involves site preparation, excavation, base installation, laying pavers, cutting edges, and sealing.
Day 1: Excavation and site preparation (removing old materials, grading, and compacting).
Day 2: Installing the base layer (gravel, sand, and compacting).
Day 3-4: Laying pavers and cutting edges for a proper fit.
Day 5: Sanding joints, compacting pavers, and sealing.
With no delays or complications, a single skilled worker can complete the project in approximately five days, but additional time may be needed for intricate patterns or weather-related delays. |
Pro Services |
Answer: Two days Explanation: There are several factors that would alter this. |
Jack of trades services |
|
ProMatcher |
Answer: Four days Explanation: While it's possible for one person to complete the installation within three to four days, it's key to consider the complexity of the project, the skill level of the installer, and any various factors that could impact the timeline. Consulting with a professional contractor can provide a more accurate estimate based on your specific project requirements. |
Construction Services & Repairs |
Answer: Four days Explanation: Several days to lay the base, 2 to lay pavers and cut edges. |
TJB-INC Landscape & Drainage Contractor |
Answer: Not sure Explanation: I work almost inside Job and Bigger Pieces |
AMG Flooring & Paint, Inc. |
|
ProMatcher |
Answer: Two days Explanation: One day preparing, Excavating, leveling
the second day laying pavers |
New Exteriors LLC |
Answer: Six days Explanation: Nearly 800 pavers. That's alot before dinner time |
Kon-Krete Specialist |
Answer: Four days Explanation: Ussually its more than one person.but it would take 3 to 4 days for one person to install this square footage |
Concrete Designs |
|
ProMatcher |
Answer: One day Explanation: Really nothing to it as long as he's moving along and not take as many cigarette breaks as normal lol. Shouldn't take more then a day or else your in the wrong industry. |
SouthPac Construction |
Answer: Three days Explanation: At a rate of 400 per day, plus some form work and so forth, three days should be ample.
This could be a trick question though. It doesn't specify the hours worked in a day, so let's say the brick layer works a full 24 hours. This should be ample time to lay the driveway; Just keep the coffee coming. |
Dolphin Pools |
Answer: Six days Explanation: to do it this job from demodition grade put base and sand and layout brick sealing with polysand pass the compact plate wash and sealing |
alvaradomasonry |
|
ProMatcher |
Answer: Not sure Explanation: This question is to vague to answer correctly. There is no indication what the sub surface is. Does excavation need to be done? What is the level of compaction? How close is the job site to where the pavers are stored. But to provide an answer 800 square feet of pavers could be installed in a 1-2 days. |
A New Design Landscape & Stone, Inc. |
Answer: Seven days Explanation: You have to prep for the blocks that's one maybe two days and then figure 200 square feet a day there you go six seven days |
Foster Construction |
Answer: Three days Explanation: The amount of time, can vary depending on the particular paver being used. |
Land Tech Landscapes |
|
ProMatcher |
Answer: One day Explanation: I have did it in 1day |
HAMMER & SONS CONSTRUCTION |
Answer: Not sure Explanation: Its all about the accessibility of the materials and if there is any slopes or drain that must be worked |
h and h company |
Answer: Three days Explanation: ground preparation along with installation of pavers can take hours for a few square feet. |
Concrete & Beauty Design |
|
ProMatcher |
Answer: Four days Explanation: An experienced installer installing proper base and a basic paver pattern should be able to install 800 square feet in 4 days. |
Cornerstone Land Management |
Answer: Three days Explanation: if were all ready prepped it could be done in 2 days |
Rock Star Masonry |
Answer: Not sure Explanation: This anser has too many variables to give an answer without seeing the project first. |
Axiom Construction |
|
ProMatcher |
Answer: Two days Explanation: First day need to dig 8 to 9 inches deep just because it's a driveway. Then need to install 8 inches of compacted abc stone, need to compact with a ply tamp.second day, need to install 2 inches of sand and start installing your pavers and to make sure they are level. |
Garcias Concrete Service LLC, |
Answer: Seven days Explanation: A driveway install can have many variables which can dictate a drastic difference in time. Expect 1-2 days for excavation, 1-2 days for the base installation, 2-3 days for pattern layout, and 1-3 days for cuts, final adjustments, and site cleanup. |
Blue Lotus Landscaping |
Answer: Four days Explanation: 800 sq feet of pavers should be able to be cut out, gravel installed, labor and cut in within a four day period. |
Evans Landscapes &Design Inc. |
|
ProMatcher |
Answer: Four days Explanation: These are time consuming |
S7 CONCRETE |
Answer: Three days Explanation: The size of the paver would allow completion of this task in about 4 days. However there are circumstances that would require a longer install |
Salinas Lawn Services |
Answer: Two days Explanation: Prep work |
dlb construction |
|
ProMatcher |
Answer: Five days Explanation: You will need to order 20 yard dumpster 1/2 day, 2 general laborer's 2 days prep work and clean-up. @ day laborer's to lay brick pavers 1 day and 1/2, 1 day to finish sand and concrete mix topping and clean up. |
JE Restoration, LLC |
Answer: Three days Explanation: www.facebook.com/eliteconst |
Elite Construction |
Answer: Three days Explanation: It could take 2 -7 days depending on their level of expertise. We are ICPI Certified Paver Installer and could have a job like this done in 1-2 days. Depending on the site conditions. |
Quality Contractors |
|
ProMatcher |
Answer: Two days Explanation: This is a two day job for 1 person |
Carvalho Pavers |
Answer: Four days Explanation: depends on weather and such. |
Major League Construction |
Answer: Four days Explanation: Always allow an extra day for clean up, about four days should do it. |
Robbie Lee Construction |
|
ProMatcher |
Answer: Three days Explanation: It really depends on the design,edge,grade,etc. Typically a straight drive with a basic patern on level ground should be a three day job. |
Unique visions landscape design |
Answer: Two days Explanation: One day to prep area and a second to install |
Greener Touch Landscaping llc |
Answer: Five days Explanation: I would never expect one person to handle the project, the prep work, the overall work load should be performed with proper compacting equipment, leveling equipment etc... I Would not bid the work out for a one man crew so I would say have fun for a week or so... |
Nu-Face of PA |