Answer: One day Explanation: Experience is the key! |
Sod Sales Direct |
Answer: Five days Explanation: Depending |
GL LANDSCAPE SERVICE LLC |
Answer: Five days Explanation: Installing a 40' x 20' brick driveway (800 sq. ft.) using 12"x10" pavers is a labor-intensive process for one person. The job involves site preparation, excavation, base installation, laying pavers, cutting edges, and sealing.
Day 1: Excavation and site preparation (removing old materials, grading, and compacting).
Day 2: Installing the base layer (gravel, sand, and compacting).
Day 3-4: Laying pavers and cutting edges for a proper fit.
Day 5: Sanding joints, compacting pavers, and sealing.
With no delays or complications, a single skilled worker can complete the project in approximately five days, but additional time may be needed for intricate patterns or weather-related delays. |
Pro Services |
|
ProMatcher |
Answer: Three days Explanation: If the driveway has already been prepared. Meaning that the surface is flat, required membranes have been applied and all other best practices are already met this is a reasonable timeline with 2 installers. The tile can be installed in two days and the final day is to add the grout and required sealants. |
Rafael Tile Works |
Answer: Four days Explanation: While it's possible for one person to complete the installation within three to four days, it's key to consider the complexity of the project, the skill level of the installer, and any various factors that could impact the timeline. Consulting with a professional contractor can provide a more accurate estimate based on your specific project requirements. |
Construction Services & Repairs |
Answer: Four days Explanation: Several days to lay the base, 2 to lay pavers and cut edges. |
TJB-INC Landscape & Drainage Contractor |
|
ProMatcher |
Answer: Three days Explanation: (26% of 83 votes): three days |
Chos cortez construcción LLC |
Answer: Two days Explanation: One day preparing, Excavating, leveling
the second day laying pavers |
New Exteriors LLC |
Answer: Six days Explanation: Nearly 800 pavers. That's alot before dinner time |
Kon-Krete Specialist |
|
ProMatcher |
Answer: Seven days Explanation: Of course it depends on equipment available and existing driveway proper excavation of materials. Adequate base added and compacted in layers as well as hauling away excess material
It can take a couple of wwwks or as little as 3 or 4 days with experience and equipment |
Mr Falls Tree Experts |
Answer: One day Explanation: Really nothing to it as long as he's moving along and not take as many cigarette breaks as normal lol. Shouldn't take more then a day or else your in the wrong industry. |
SouthPac Construction |
Answer: Three days Explanation: At a rate of 400 per day, plus some form work and so forth, three days should be ample.
This could be a trick question though. It doesn't specify the hours worked in a day, so let's say the brick layer works a full 24 hours. This should be ample time to lay the driveway; Just keep the coffee coming. |
Dolphin Pools |
|
ProMatcher |
Answer: Not sure Explanation: It would depend on site conditions as well as the individual. It could take a few days or longer. If conditions are good this type of job could take approx. 2 days. |
Design4 |
Answer: Not sure Explanation: This question is to vague to answer correctly. There is no indication what the sub surface is. Does excavation need to be done? What is the level of compaction? How close is the job site to where the pavers are stored. But to provide an answer 800 square feet of pavers could be installed in a 1-2 days. |
A New Design Landscape & Stone, Inc. |
Answer: Seven days Explanation: You have to prep for the blocks that's one maybe two days and then figure 200 square feet a day there you go six seven days |
Foster Construction |
|
ProMatcher |
Answer: Three days Explanation: Safe to say three days! One day is prep and two for install |
DIRTCO CONSTRUCTION |
Answer: One day Explanation: I have did it in 1day |
HAMMER & SONS CONSTRUCTION |
Answer: Not sure Explanation: Its all about the accessibility of the materials and if there is any slopes or drain that must be worked |
h and h company |
|
ProMatcher |
Answer: Not sure Explanation: We don't do brick driveways. We do only stone installations |
1964 |
Answer: Four days Explanation: An experienced installer installing proper base and a basic paver pattern should be able to install 800 square feet in 4 days. |
Cornerstone Land Management |
Answer: Three days Explanation: if were all ready prepped it could be done in 2 days |
Rock Star Masonry |
|
ProMatcher |
Answer: Two days Explanation: First day need to dig 8 to 9 inches deep just because it's a driveway. Then need to install 8 inches of compacted abc stone, need to compact with a ply tamp.second day, need to install 2 inches of sand and start installing your pavers and to make sure they are level. |
Garcias Concrete Service LLC, |
Answer: Seven days Explanation: A driveway install can have many variables which can dictate a drastic difference in time. Expect 1-2 days for excavation, 1-2 days for the base installation, 2-3 days for pattern layout, and 1-3 days for cuts, final adjustments, and site cleanup. |
Blue Lotus Landscaping |
Answer: Four days Explanation: 800 sq feet of pavers should be able to be cut out, gravel installed, labor and cut in within a four day period. |
Evans Landscapes &Design Inc. |
|
ProMatcher |
Answer: Four days Explanation: These are time consuming |
S7 CONCRETE |
Answer: Three days Explanation: The size of the paver would allow completion of this task in about 4 days. However there are circumstances that would require a longer install |
Salinas Lawn Services |
Answer: Two days Explanation: Prep work |
dlb construction |
|
ProMatcher |
Answer: Five days Explanation: You will need to order 20 yard dumpster 1/2 day, 2 general laborer's 2 days prep work and clean-up. @ day laborer's to lay brick pavers 1 day and 1/2, 1 day to finish sand and concrete mix topping and clean up. |
JE Restoration, LLC |
Answer: Three days Explanation: www.facebook.com/eliteconst |
Elite Construction |
Answer: Three days Explanation: It could take 2 -7 days depending on their level of expertise. We are ICPI Certified Paver Installer and could have a job like this done in 1-2 days. Depending on the site conditions. |
Quality Contractors |
|
ProMatcher |
Answer: Two days Explanation: This is a two day job for 1 person |
Carvalho Pavers |
Answer: Four days Explanation: depends on weather and such. |
Major League Construction |
Answer: Four days Explanation: Always allow an extra day for clean up, about four days should do it. |
Robbie Lee Construction |
|
ProMatcher |
Answer: Three days Explanation: It really depends on the design,edge,grade,etc. Typically a straight drive with a basic patern on level ground should be a three day job. |
Unique visions landscape design |
Answer: Two days Explanation: One day to prep area and a second to install |
Greener Touch Landscaping llc |
Answer: Five days Explanation: I would never expect one person to handle the project, the prep work, the overall work load should be performed with proper compacting equipment, leveling equipment etc... I Would not bid the work out for a one man crew so I would say have fun for a week or so... |
Nu-Face of PA |